A proposed data center in Salem has become the focus of a zoning dispute after the city’s zoning board of appeals canceled the project’s building permit amid opposition from residents.
Prime Group Holding, an upstate New York company that owns the 30-acre Shetland Park, received a building permit in May. The project later drew criticism after residents learned that the facility was substantially larger than the operation initially described to city officials.
“There’s probably a place for data centers. It’s probably not in a dense city like Salem.” — Ty Hapworth, Salem city councilor
The company first proposed a smaller facility, identifying its intended occupant only as an unnamed information-technology services company. After the permit was issued, the planned operation was expanded to roughly the size of a drugstore. The revised design called for three diesel generators for backup power, compared with one generator in the earlier proposal.
The zoning board withdrew the permit in September as residents raised questions about whether Prime Group had fully disclosed its plans. The dispute reflects a broader change in public attention toward data centers, including smaller facilities that historically attracted little notice.
Concerns over infrastructure
Residents’ concerns include the project’s possible effect on local water supplies, electricity rates, noise and air pollution. Data centers can require substantial electricity and cooling, although the size and operating requirements of facilities vary. The proposed Salem project is not described as one of the massive hyperscale campuses being developed elsewhere for artificial-intelligence systems.
There are about 3,000 data centers in the United States, according to the Pew Research Center. Many are relatively small, including a facility located above the Macy’s department store in Boston’s Downtown Crossing that has operated for nearly 30 years and uses limited cooling water and electricity.
- Prime Group received a Salem building permit in May for the Shetland Park project.
- The zoning board of appeals canceled the permit in September after residents challenged the project.
- The expanded proposal called for three diesel backup generators instead of one.
The Salem controversy follows opposition to much larger data center proposals in New England. Public resistance halted a proposed $4 billion project in Westfield, Massachusetts, in October. Residents in Sutton, Massachusetts, also opposed a data center proposal backed by the Kraft Group.
In Salem, the permit dispute centers on how the project was presented to city officials and residents, as well as the infrastructure demands associated with its expanded design. Hapworth said the city’s density should be considered when data center proposals are evaluated.